The next phase for building a new Fall Brook Elementary School is about to begin. According to Craig DeCarlo, senior project manager for Left Field, the owner’s project manager, the Leominster project recently completed its early site package. Construction crews relocated underground water, sewer and storm drainage lines to prepare the site for the new school building. “The early site package was completed successfully, and the project team extends its sincere thanks to the Fall Brook and Samoset communities for their patience, flexibility and support throughout the construction activities,” said DeCarlo.